Jun. '00 - November '02
|
- PT. INTERNATIONAL NICKEL (INCO) INDONESIA
Construction Services - Construction Manager
Accountable and responsible to :
- Manage all Operating and Capital Construction section within quality, cost, and delivery (QCD) aspect, including all jobs conducted at plant (field) and Construction Services workshop.,
Operating Construction services covering :
- construct and maintain new civil facilities such as new building, tank, warehousing yard, house, water, oil, and waste pipe line, public road, airport, and port facilities, etc
- civil and mechanical maintenance of plant facilities such as furnaces, dryer, kiln, converter, hydro power plant, and other supporting utilities,
- deliver rigging and transporting equipment, such as crane (20 – 150 Ton Capacity), boom truck, trailer, forklift, etc.
- inspect all civil facilities such as bridge, oil and water pipe line, overhead crane), and develop its maintenance action plan.
- Manage monthly and yearly Operating Constuction budget. There are consist of operating and repair budget,
- Give constructability advice for tendering, evaluate tender price, and technical aspect ,
- Achieve of Construction Services Safety Target that implemented in Safety Calender, Produce and Review Safety Operating Procedure, etc.,
- Develop QCD metric/service key performance index to measure Operating Construction services to the Customers,
- Conduct coaching session to Operating Construction Supervisor,
- Implement Performance Development Review/Skill Audit for all Operating Construction crews,
- Develop, Sozialise, and Implement “Service Level Aggreement” with Operating Construction Customers.
|
|
Sept '02 - At present
|
- PT INTERNATIONAL NICKEL (INCO) INDONESIA
Senior Supervisor for Mining Department (Civil Works, Equipment Move and Refuelling Section)
Accountable and responsible to :
- Manage all Civil works around mining area and maintain of civil facilities within good quality, cost, and commitment delivery,
- Manage re-fueling all mining and process plant equipments (130 units main equipment),
- Execute engineering plan for quarring and its preparation such as drilling and hauling management,
- Achieve of Mining Safety Target that implemented in Safety Calendar, Develop and Review Safety Operating Procedure, etc.
|
|
Jun. '00 - November '02
- PT. INTERNATIONAL NICKEL (INCO) INDONESIA
Construction Services - Construction Manager
Accountable and responsible to :
- Manage all Operating and Capital Construction section within quality, cost, and delivery (QCD) aspect, including all jobs conducted at plant (field) and Construction Services workshop.,
Operating Construction services covering :
- construct and maintain new civil facilities such as new building, tank, warehousing yard, house, water, oil, and waste pipe line, public road, airport, and port facilities, etc
- civil and mechanical maintenance of plant facilities such as furnaces, dryer, kiln, converter, hydro power plant, and other supporting utilities,
- deliver rigging and transporting equipment, such as crane (20 – 150 Ton Capacity), boom truck, trailer, forklift, etc.
- inspect all civil facilities such as bridge, oil and water pipe line, overhead crane), and develop its maintenance action plan.
- Manage monthly and yearly Operating Constuction budget. There are consist of operating and repair budget,
- Give constructability advice for tendering, evaluate tender price, and technical aspect ,
- Achieve of Construction Services Safety Target that implemented in Safety Calender, Produce and Review Safety Operating Procedure, etc.,
- Develop QCD metric/service key performance index to measure Operating Construction services to the Customers,
- Conduct coaching session to Operating Construction Supervisor,
- Implement Performance Development Review/Skill Audit for all Operating Construction crews,
- Develop, Sozialise, and Implement “Service Level Aggreement” with Operating Construction Customers.
|
|
Jun '02 - At present
|
- PT INTERNATIONAL NICKEL (INCO) INDONESIA
Assist. Project Manager for Koro Stripping Project and Project Manager for Loraine Stripping Project
Accountable and responsible to :
- Achieve production target (20,000 BCM/day) and maintain actual production report to short term planning,
- Achieve zero accident target during the project execution,
- Liason between PTI and Contractor and ensure contractor following all aspect in the contract.
|
|
|
Nov. '99 - Jun. '00
|
- PT INTERNATIONAL NICKEL (INCO) INDONESIA
Organization Effectiveness Team
Accountable and responsible to :
- Assist Organization Effectiveness Champion to develop and implement new Technical Services Organization,
- Develop and manage Technical Services initiative projects,
- Develop Technical Services Project initiative database,
- Socialize Organization Effectiveness Review to achieve Company Mission, Goal, and Objective.
|
|
Oct. '98 - Oct. '99
|
- PT INTERNATIONAL NICKEL (INCO) INDONESIA
Supervisor for Civil-Mechanical at Central Maintenance Department
Accountable and responsible to:
- Supervise all Civil-Mechanical maintenance works at all plant areas such as stock pile area (ming facilities), process and operation equipments (from dryer, kiln, furnace, and converter), hydropower and utilities maintenance,
- Supervise all Contractor and Sub-contractor for Town Facilities Maintenance,
- Supervise for Heavy Equipment Operation, consist of 1 unit 250T Manitowoc Crane, 2 Units Grove Crane (20 T & 130 T), 3 Units Volvo Trucks, 2 Units Forklift, 1 Unit Trailer (30 T), and Loader (Cat 966),
- Supervise for Minor Equipment Operation, such as welding machine, air compressor, etc.,
- Prepare annual budget for Heavy Equipment and Minor Equipment maintenance and operation,
- Suprvise for Operation back charge of Heavy Equipment and Minor Equipment,
- Develop sub-ordinat to understand and familiar using MIMS,
|
|
Sept. '98 - Oct. '98
|
- PT. INTERNATIONAL NICKEL (INCO) INDONESIA
Engineering Department
- Assist to Senior Supervisor for Wet Electrode Modification of Furnace # 1 and 2, Assist to Civil Engineer Specialist for Cloud Seeding Project,
- Project Engineer for Mobile Equipment Maintenance Construction Stage II,
- Civil Engineer for Apron Feeder of Dryer # 2 Overhaul.
|
|
Aug '97 - Aug. '98
|
- PT INTERNATIONAL NICKEL (INCO) INDONESIA
Assigned at Process Plant, Maintenance, Utilities, and Logistic Department) - Assigned to expose Process Plant Operation covering 5 major areas (Dryer, Reduction Kiln, Furnace, Converter, and Process Technology), to study problem solving in Plant Operation, and to be a seconded in Maintenance, Utilities and Logistic Department)
Project involved during the assignment :
- Larona Canal and Batubesi Dam Monitoring,
- Preparing Inspection Report and Maintenance Suggestion for Structural condition at Furnace and Converter Area,
- Structural Check of 3Ton Calcine Craine Facility of Furnace # 1,
- Dry Electrode and Gas Cooling Chamber of FCE # 2 Replacement,
- Chalet Houses Suitability Survey,
- Process Technology Laboratorium Effluent Improvement,
- Routine Maintenance Projects held by Plant Maintenance and Central Maintenance Department (such as maintenance of Screening Station # 2, Lippmann Crusher Demolition, Partial Replacement of Converter Brick, etc.).
|
|
June '96 - July '97
|
- PT INTERNATIONAL NICKEL (INCO) INDONESIA
Civil Engineer (Project Engineer) for Engineering Department
Principal project involved :
- Bailey Bridge Replacement,
- Town Site and Plant Site Asphalting,
- Replacement steel and cable for converter, furnace, kiln, and dryer area,
- Top Shop and Washpad Construction - MEM Stage I,
- Design and Improvement of process yard drainage and Mangkasa Point oil traps,
- Design and Supervision of Calcine Crane access platform construction,
- Dryer Office Construction,
- Larona Canal Major Refurbishmenet,
- Supervision of Electrical Tower # 39 erection,
- Supervision of Foundation Construction of Furnace # 1 & 2 Reactor,
|
|
Aug' 93 - May '96
|
- >PT WIRATMAN & ASSOCIATES, JAKARTA MAIN OFFICE
Civil Engineer for Power Engineering Division
Prinsipal Project Engaged :
- Up dating of Sumatera Hydro Power Plant Study, State Electricity Company (PT. PLN),
- Hydrological survey for Werba Micro Hydro Power Plant, Fak-fak, Irian Jaya, State Electricity Company (PT. PLN),
- Feasibility Study of Kayan-2 Hydro Power Project, East Kalimantan, State Electricity Company (PT. PLN),
- Feasibility Study of Rongi Micro Hydro Power Plant, South East Sulawesi, State Electricity Company (PT PLN),
- Assist to prepare project proposal for Detailed Design of Merangin-2 Hydro Power Pland and Up dating Indonesian Hydro Electric Potentials.
|
|
Jun '89 - July '93
|
- PT. WIRATMAN & ASSOCIATES, SURABAYA BRANCH
Assistant of Civil Engineer
Principal Project Engaged :
- Supervision of Tuban Port Construction, PT. Semen Gresik,
- Supervision of Preheater IIA Steel Erection,
- East Java Hydrogeological Mapping, Ministry of Public Works, East Java Groundwater Development Project,
- Shangri-la and Westin Hotel Construction,
- Supervision of East Java Irrigation Networks Rehabilitation Project, East Java Irrigation Project,
- Survey, Investigation, and Design for Jabung (Madiun) Irrigation Project,
- Supervision of Dupak Rukun Fly Over Construction, East Java Road Betterment Office,
- Porong River Rehabilitation Project, Brantas River Project.
|
|
Trainings, Courses, and Seminars
|
- Microsoft Project '98, held by IVERSION - Jakarta, September 1998,
- Accident and Incident Investigation, Cause and Effect of Loss, Management Control of Loss, held by HRD Dept. PT, INCO, 1998,
- Train the Trainer, February 1998,
- Seminar on Hubungan Industrial Pancasila, 1997,
- Seminar on Project Management, held by PT INCO-Kerry Management (USA), 1996,
- Soil Nailing Overview, held by Harding Lawson Associates - USA, Jakarta 1994,
- Seminar on ISO 9000, held by Asian Bussiness Services, Jakarta 1994,
- Seminar on Communication, Leadership, and Project Evaluation, held by PT CAA Management Consultant, Malang, 1993,
- Seminar on Trends of Structural Concrete Design Toward 21st Century, Surabaya, 1992,
- Short Course on Coastal Engineering, held by ITS - TU Delf, September 1988,
- Pre-advance English Course, PPIA Surabaya 1988-1991, General English Course for Employee and English for Supervisor, held by HRD PT INCO, 1996-1997,
- Environmental Consultant Staff Orientation, held by Indonesian Consultant Association (INKINDO), Malang 1991,
- Construction Management, Value Engineering and Project Supervision Seminar, held by ITS Surabaya, 1988.
|
|
Job Training
|
- Supervision of Mt. Semeru Flood Control Construction, Mt. Semeru Project, Lumajang-East Java, 1998,
- Supervision of Surabaya River Rubber Dam Construction, Brantas River Project, East Java, 1992,
- On the job training to operate "Wiratman Accounting Computer Programs", held by Finance and Administration Division, 1992,
- Design of Mojokerto Groundwater Irrigation System, East Java Groundwater Development Project, 1993.
|
|
Selected Extra and Intra Curricular Activities
|
- 2nd Winner of Scientific Writing Competition (Easat Java Region) with theme "Saving Energy", held by ITS, 1992,
- Nominator for Compression Strenght of Concrete Competition, held by Department of Public Works (East Java Region), 1992,
- 1st Winner of Compression Strenght of Concrete Competition, held by Indonesian Civil Engineering Students Forum (FKMTSI), 1992,
- Recipient of PT Mobil Oil Corporation and PT Djarum Kudus Scholarship,
- Committee of Bachelor Degree Orientation, 1991,
- Advanced Student Organization and Management Training, IPB Bogor, 1989,
- Member of Student Representative Coordination Board (BKK) ITS, 1988/1989,
- 4th Winner of Scientific Writing Competition, held by ITS, 1988,
- Pre-advanced Student Organization and Management Training Region VII & VIII), Airlangga University Surabaya, 1988,
- 2nd Winner of Scientific Writing Competition, Muhammadiyah Students Association, Surabaya, 1988,
- Steering Committee of Orientation Study, Hydro Engineering Students Association, ITS Surabaya, 1988,
- Chairman of Student Senate, Department of Civil Engineering, ITS Surabaya, 1987/1988,
- Secretary of Student Senate, Department of Civil Engineering, ITS Surabaya, 1986/1987.
|
|
Other Abilities
|
- Able to operate computer programs :
- Word Processor : WS, WordPerfect, MS-Word
- Spreed Sheet : Lotus, Excel,
- Structural : Microfeap, SAP ’90
- Project Control : Microsoft Project, Primavera for Windows
- Other : HTML, Assembler, MIMS
|