Project Start Date: Sat 4/24/04
Project Finish Date: Thu 4/28/05
Resources and Assignments | Start | Finish | Work |
---|---|---|---|
Lisa | Mon 4/26/04 | Thu 4/28/05 | 2,116 hrs |
Identify goals and objectives | Mon 4/26/04 | Fri 4/30/04 | 40 hrs |
Prepare project charter | Wed 5/5/04 | Fri 5/7/04 | 24 hrs |
Estimation of hours for internal staff | Thu 4/29/04 | Mon 5/3/04 | 24 hrs |
Write a brief summary of the results | Mon 5/3/04 | Mon 5/3/04 | 0 hrs |
Change in software cost | Mon 4/26/04 | Tue 5/4/04 | 56 hrs |
Discuss team morale | Wed 5/5/04 | Wed 5/5/04 | 8 hrs |
Meeting with project sponsor | Thu 5/6/04 | Thu 5/6/04 | 4 hrs |
Team evaluation report | Thu 5/6/04 | Wed 5/12/04 | 40 hrs |
Prepare final project report | Fri 5/28/04 | Thu 4/28/05 | 1,920 hrs |
Richard | Thu 4/29/04 | Wed 6/2/04 | 360 hrs |
Define main function for the system | Mon 5/3/04 | Fri 5/14/04 | 80 hrs |
Provide assessment for each function | Thu 5/13/04 | Tue 5/18/04 | 32 hrs |
Summarize the results | Wed 5/19/04 | Wed 5/19/04 | 0 hrs |
Prepare business case | Fri 4/30/04 | Tue 5/4/04 | 24 hrs |
Develop WBS | Thu 5/13/04 | Fri 5/21/04 | 56 hrs |
Create Gantt Chart | Mon 5/24/04 | Tue 5/25/04 | 16 hrs |
Create network diagram | Wed 5/26/04 | Thu 5/27/04 | 16 hrs |
Create lists of prioritized risks for the project | Tue 6/1/04 | Wed 6/2/04 | 16 hrs |
Calculate new financial investment cost | Thu 4/29/04 | Tue 5/4/04 | 32 hrs |
Summarize the result | Wed 5/5/04 | Wed 5/5/04 | 8 hrs |
Prepare a lesson learned report | Fri 5/14/04 | Thu 5/27/04 | 80 hrs |
Sara | Mon 4/26/04 | Thu 6/3/04 | 552 hrs |
Define main function for the system | Mon 5/3/04 | Fri 5/14/04 | 80 hrs |
Provide assessment for each function | Thu 5/13/04 | Tue 5/18/04 | 32 hrs |
Summarize the results | Wed 5/19/04 | Wed 5/19/04 | 0 hrs |
Description of job duties and qualification | Mon 4/26/04 | Thu 4/29/04 | 32 hrs |
Describe dream team plan | Mon 4/26/04 | Wed 4/28/04 | 24 hrs |
Develop team contract | Tue 5/4/04 | Thu 5/6/04 | 24 hrs |
Develop WBS | Thu 5/13/04 | Fri 5/21/04 | 56 hrs |
Create Gantt Chart | Mon 5/24/04 | Tue 5/25/04 | 16 hrs |
Create probability/impact matrix | Fri 5/28/04 | Mon 5/31/04 | 16 hrs |
Prepare monthly progress report | Thu 5/6/04 | Thu 6/3/04 | 160 hrs |
Prepare presentation | Mon 4/26/04 | Thu 5/13/04 | 112 hrs |
Todd | Mon 4/26/04 | Thu 9/23/04 | 920.5 hrs |
Develop criteria for each function | Mon 4/26/04 | Wed 4/28/04 | 24 hrs |
Assign weights to each criterion | Thu 4/29/04 | Fri 4/30/04 | 16 hrs |
Calculate the weighted score | Mon 5/3/04 | Mon 5/3/04 | 0.5 hrs |
Summarize the results | Mon 5/3/04 | Mon 5/3/04 | 0 hrs |
Financial analysis for the project | Fri 4/30/04 | Tue 5/4/04 | 24 hrs |
Develop scope statement | Fri 5/7/04 | Wed 5/12/04 | 32 hrs |
Create probability/impact matrix | Fri 5/28/04 | Mon 5/31/04 | 16 hrs |
Create lists of prioritized risks for the project | Tue 6/1/04 | Wed 6/2/04 | 16 hrs |
Prepare milestone report | Thu 6/3/04 | Thu 9/23/04 | 640 hrs |
Calculate new financial investment cost | Thu 4/29/04 | Tue 5/4/04 | 32 hrs |
Summarize the result | Wed 5/5/04 | Wed 5/5/04 | 8 hrs |
Prepare presentation | Mon 4/26/04 | Thu 5/13/04 | 112 hrs |
Alex | Mon 4/26/04 | Thu 5/27/04 | 160 hrs |
Change in software cost | Mon 4/26/04 | Tue 5/4/04 | 56 hrs |
Report on preventing scope creep | Mon 4/26/04 | Wed 4/28/04 | 24 hrs |
Prepare a lesson learned report | Fri 5/14/04 | Thu 5/27/04 | 80 hrs |